Step 4. This step consists of analyzing photovoltaic (PV) production on site. This is computed via an online software tool called Helioscope (see Figure 5). Oftentimes, with medium to large size multifamily projects, it won’t be possible to cover the entire building's energy usage with on-site solar. Such is the case for Hampden. In these cases, it’s good to target a PV output large enough to cover a building’s miscellaneous electrical loads.
Simulated Energy Modeling
Step 5. This phase of robust energy modeling starts in schematic design and continues into construction documentation. Energy modeling will sometimes extend into the construction administration phase, if there are change orders or value engineering efforts later in the project. PTEH utilizes WUFI Passive software for advanced analysis of hydrothermal conditions while also taking shading, daylight, and climate into account.
Before schematic design ends, the CPHC will conduct a feasibility study that models out three different case studies using WUFI. This allows a cross comparison of different assembly and mechanical, electrical, and plumbing (MEP) system options. The CPHC presents these options to the client and design team in a collaborative setting to weigh the pros and cons of each option.
Case 1. Code Minimum Design. The first energy model is built to the project’s local energy code minimum requirements. This provides the design team and client with a baseline understanding of how their building would perform if no Passive House concepts were taken into consideration.
Case 2. Architectural Drawing Set. The second WUFI case study will be modeled based on the architect’s narrative for assemblies and systems. Usually, the architect’s narrative meets or exceeds the minimum energy code requirements.
Case 3. Passive House. The last energy model is designed to Passive House certification. This takes the architect's design narrative and enhances it to hit the energy reduction targets.
The target energy reduction criteria specific for 201 Hampden are listed here. These numbers are determined by Phius and are customized for 201 Hampden’s design and location.
Hampden’s Passive House Target Design Criteria:
HEATING DEMAND: 4.6 kBtu/sf/yr
COOLING DEMAND: 5.4 kBtu/sf/yr
PEAK HEATING LOAD: 3.8 Btu/hr/sf
PEAK COOLING LOAD: 2.7 Btu/hr/sf
SOURCE ENERGY CONSUMPTION: 4,683 kWh/person /yr
Below is how Hampden performed under each of the three different case study scenarios. Green text indicates numbers that meet or exceed the Phius requirements, while red text indicates points of failure.
CASE 1 - Code Minimum Design
HEATING DEMAND: 6.75 kBtu/ft2yr
COOLING DEMAND: 2.64 kBtu/ft2yr
PEAK HEATING LOAD: 7.8 Btu/hr ft2
PEAK COOLING LOAD: 2.93 Btu/hr ft2
SOURCE ENERGY CONSUMPTION: 5,583 kWh/person /yr
CASE 2 - Architectural Drawing Set
HEATING DEMAND: 2.43 kBtu/ft2yr
COOLING DEMAND: 4.36 kBtu/ft2yr
PEAK HEATING LOAD: 3.89 Btu/hr ft2
PEAK COOLING LOAD: 3.12 Btu/hr ft2
SOURCE ENERGY CONSUMPTION: 3,667 kWh/person/yr (with PV installation)
CASE 3 - Passive House
HEATING DEMAND: 1.46 kBtu/ft2yr
COOLING DEMAND: 3.63 kBtu/ft2yr
PEAK HEATING LOAD: 3.24 Btu/hr ft2
PEAK COOLING LOAD: 2.59 Btu/hr ft
SOURCE ENERGY CONSUMPTION: 3,566 kWh/person yr (with PV installation)
201 Hampden performed well in the Case 2 scenario due to the architect and design team utilizing robust assembly and system assumptions. Therefore, very little had to change to satisfy Passive House criteria in Case 3. Updates to the architectural drawing set model to achieve Passive House included a reduction in the number of windows, a higher performing HVAC system, and minor changes in assembly R-values.
In many instances, energy modeling can be used as a cost savings tool by helping teams dial in on the exact amount of insulation and performance needed to hit their Passive house targets. For 201 Hampden, the project was able to reduce the overall amount of insulation and windows that the design team had originally specified, providing some cost savings.
Step 6 & beyond. With the feasibility study completed, the CPHC continues to collaborate with the architect and design team to best detail assemblies and building systems that maintain the Passive House criteria targets. Below are the current assumptions for 201 Hampden’s building envelope assemblies. Components are listed in order from outside to inside (see Figure 6).