Otherwise, the retrofit essentially builds a new envelope—walls, roof, and insulated first floor— within the existing one. Even the existing single-pane, double-hung windows will remain in the brick wall, acting as a sort of rainscreen for the triple-pane Alpen windows installed within our new inner envelope walls. The intensive interior work to the building required that it be vacant. We coordinated the retrofit with the remote work circumstances made necessary by the COVID-19 pandemic.
Partitioning the Building
A key early decision involved which elements of the building were to remain within the interior conditioned area, versus outside of it. The first decision was to leave the basement outside of the equation. Excluding it from the conditioned envelope makes sense, as the basement is characteristically damp for its age and its location, which is adjacent to a river, and there is no vapor barrier below its rat slab floor. The basement will house only large storage items, including the main electrical panel and a new heat pump water heater, which is expected to provide some key dehumidification. The basement ceiling will be insulated with 9 inches of dense-pack cellulose, installed above a new vapor-permeable air barrier.
The three main floors are laid out as separate tenancies, with two fire stairs connecting them that are tied into the existing exterior walls. In order to avoid complicated air sealing around this stair structure and minimize the interior conditioned area, we opted to leave these stairs outside of the conditioned envelope. Instead, the air barrier will run straight up the interior side of the newly insulated stairwell walls, behind a new insulated 2x6 wall cavity.
Refining the Ideal Wall and Roof Assemblies
Treating the existing roof and brick exterior walls as a shell, we have focused on creating thermally-robust assemblies on the interior. For the exterior walls, addressing the brick was the first challenge. After patching and filling areas that were structurally compromised, the contractors applied Sto Gold Coat, a fluid-applied air barrier, to the interior surface. This coating will act as the first line of defense against air leakage, while—given its vapor permeability—allowing the bricks to still dry out as part of our vapor-open wall assembly. The R-38 assembly includes a 2x4 framed wall held 3.5 inches off of the existing brick, with the resulting 7-inch cavity to be filled with dense-pack cellulose. A vapor-variable SIGA air barrier is located in between this 2x4 framed wall and a 2x3 service cavity wall, which will be filled with additional mineral wool insulation. This assembly will accommodate shifting electrical and data services in the exterior walls, as occupants and building use change over time, without sacrificing the air barrier.
After much back and forth with the contractor, PHIUS verifier, WUFI modeler, PHIUS technical team, and our staff, we opted for a vapor-closed roof assembly below our existing roof. This will include 3.5 inches of closed-cell spray foam below the existing roof sheathing and between the existing 5x5 rafters, with an additional 9.5 inches of dense-pack cellulose below, and a small insulated service cavity for wiring. The entire assembly will achieve a total R-value of approximately 60. We have also added closed-cell spray foam at the tops of the brick walls, where large gaps existed between the wall and roof eaves. While we would have ideally pursued a vapor-open and foam-free roof assembly, it became clear that given the inconsistencies with the roof framing and materials, that approach would have left us too vulnerable to water penetration. The additional R-value offered by the spray foam is also quite valuable, given the limited space at the eaves.